Payment of Expenditure

To request payment of an expenditure on a grant, the principal investigator should send to the Accounts Payable Office: (1) the original invoice stapled to a purchase order (if available), and (2) a copy of the invoice. At minimum, the subcontract must include the following

  • Scope of work.
  • Identification of the proposed subcontractor, contact person, address, and phone number.
  • The proposed subcontract price.
  • The methodology proposed by the principal investigator (PI) to monitor execution of the subcontract.
  • Clause for changes that require written approval.
  • Clause identifying payment method to subcontractor.
  • The assigned purchase order number.
  • Authorized start and end dates.
  • Termination clause.
  • Liability clause.
  • Clause stating the prime award terms and conditions that apply to the subcontract.
  • Subrecipient audit clause.
  • Other information as required by the contract officer and University reviewers.