Final reports and financial reconciliation are required to officially close a sponsored award.

Has your award expired, been terminated, or has the study ended? Certain actions are required to ensure the award can be officially closed.

Awards may close:

  • On the expected end date

  • When project work or deliverables are completed

  • Following early termination

In all cases, timely close-out is required to meet sponsor, financial, and compliance obligations.

Close-out Responsibilities

Successful award close-out requires coordination among the department, the principal investigator, Sponsored Programs Administration (SPA), and Sponsored Projects Accounting and Compliance (SPAC).

Key Close-out Actions

  • Review the award document for final report and invoice due dates.
  • Deadlines vary by sponsor and may differ for technical and financial reports.

  • Request final invoices from all subrecipients.
  • Ensure invoices are received, reviewed, approved, and paid.
  • Confirm that required subrecipient technical, invention, and property reports have been submitted.

Financial reconciliation confirms that all project costs are accurate, allowable, and properly reported.

Departments must:

  • Review the award document to confirm final invoice and financial report deadlines.
  • Reconcile the project account in a timely manner.
  • Work with SPAC on sponsor payments, invoicing, and submission of final financial reports.
  • Ensure all outstanding charges are posted and reviewed before close-out.

Sponsors require one or more final reports to document the outcomes of the project and confirm compliance with award terms.

Technical / Scientific Report

  • The final project report is the responsibility of the Principal Investigator.
  • NIH awards require submission of a Research Performance Project Report (RPPR).
  • For non-federal sponsors, technical reports may be submitted directly to the sponsor, with a copy (preferably PDF) provided to SPA.

Invention Report

  • Many sponsors require disclosure of inventions developed using award funds.
  • The PI completes the sponsor’s invention report form or provides invention or “no invention” information to SPA.
  • Similar reports must be obtained from each subrecipient investigator.
  • SPA submits the report after verification by UMB’s Office of Technology Transfer.

Property / Equipment Report

  • Some sponsors require a final equipment or property inventory report.
  • Completion of the report is the responsibility of the department.
  • Reports are signed by a UMB-authorized official in Financial Services.
  • Contact the Capital Equipment Inventory section of the Office of Financial Services for assistance.

  • A no-cost extension may be requested if project work is continuing and funds remain available.
  • Requests must be submitted before the award end date and are subject to sponsor approval.