Timeline

January 2018
Funding identified for Counseling Center and Campus Life Services renovation project.

February 2018
Site visit to Towson University’s Student Counseling Center for research and design ideas.

March – August 2018
Design and stakeholder town hall meetings. Campus Life Services leadership met with over 15 faculty, staff, and student groups to discuss the future needs of the Counseling Center and the Campus Life Services departments.

October 2018
Event Services Department relocated permanently to the lower level of the Campus Center, Room 001.

February 2019
Campus Life Business Services relocated permanently to the lower level of the Campus Center, Room 003.

March 2019
Educational Support and Disability Services Department moved temporarily until construction is completed, to Health Sciences Library, Room 201F.'

April 2019
Student Development and Leadership Deprtment moved temporarily until construction is completed, to room 506. You can access this office through the 4th floor. 

May 2019
Interprofessional Student Learning and Service Initiatives (ISLSI) moved temporarily until construction is completed, to room 223. 

Baltimore City Department of Public Works approved the renovtion project. 

June 2019
Preparation for demolition to begin in Suite 302 and Room 311.